Question:

Several processes in the Monitoring and Controlling process group include  change requests. Which of the following is incorrect?

A Approved change requests are an output of the Perform Integrated Change Control and Monitor Risks processes.
Explaination

Approved change requests are an output of the Perform Integrated Change Control process but not of the Monitor Risks process.