Question:

Stakeholder influence is highest within a project during which stage?

A Initial phase
Explaination

At the beginning of a project ambiguity is at its peak. Stakeholders have a great deal of input into this. As the project progresses and work is underway, the cost of change increases and the volume of change begins to decrease. As this is the case, stakeholders are most likely to get their requests for inclusion and changes approved during the initial phase of the project.