Question:

The project charter has just been accepted. What comes next?

A Perform stakeholder analysis
Explaination

The project charter is generated at the start of a project. Before we can move forward in planning or building out the backlog of the project, there is one key activity that a project manager should perform at the start of a project—building out the stakeholder register. This is created as a result of performing stakeholder analysis.