The project funder asks the project manager to validate that the product scope has been met. What will the project manager practice to measure the completion of the product scope?

A Product requirements
Explaination

Completion of the product scope is measured against the product requirements, whereas completion of the project scope is measured against the project management plan. Although requirements documentation is technically a correct answer, product requirements is a far more specific answer.