The project management plan may inquire changes and updates as the Planning processes proceed. These updates are decided upon and operated through which of the following?

A Perform Integrated Change Control process
explanation

The changes to the project management plan (and subsidiary plans within it) are dispositioned and managed through the Perform Integrated Change Control process.