The project manager has just determined that three functional managers with a high interest in the project hold a particularly high degree of influence in the distribution of enterprise resources. In what activity is the project manager included?

A Identifying stakeholders
Explaination

The project manager is in the process of carrying out stakeholder analysis and is evaluating the level of interest and influence of stakeholders. In this scenario, the project manager is carrying out the Identify Stakeholders process.