The project processes are iterative, are deliverable oriented, and interact with each other. Shewhart and Deming developed a concept that reflects this idea. Select the name of this cycle?

A Plan-Do-Check-Act
Explaination

The Plan-Do-Check-Act cycle was developed by Shewhart and later refined by Deming. It reflects the iterative, results-oriented, and interactive nature of the project process groups.