Question:

The project team has had to re-architect a product that did not fulfill project standards. This has led in a one-week schedule delay, in addition to the cost of rework. This is an instance of:  

A Poor quality 
Explaination

The correct answer is poor quality. Remember that quality also looks to remove waste and non-value-added processes. It looks to improve processes and make sure that project requirements are being met.