Question:

The project team recently joined in a working session to examine and document the effectiveness of risk responses in addressing overall project risk. What is this working session, or meeting, named? 

A Risk review 
Explaination

This describes a risk review, which is a tool and technique used within the Monitor Risks process, as part of “meetings” held. According to the PMBOK® Guide, risk reviews are scheduled regularly and should evaluate and capture whether risk responses implemented are effective in dealing with identified project and individual risks.