Question:

The project team recently participated in a working session to determine the costs connected with individual activities. To generate a more accurate estimate, they divided each activity further into smaller chunks. What will this activity produce? 

A Cost estimates 
explanation

The project team is participating in bottom-up estimating, which will produce activity cost estimates. This activity is associated with the Estimate Costs process. Basis of estimates may also be generated through this session; cost estimates, however, are the primary end outcome of the activity.

Related Information

Comments

edenegayle

4 years ago

I’m not sure how this app is accurate, simple & effective along with FREE? But I’m so grateful. Getting professional qualifications can be so expensive & daunting to tackle. This test taking, review-type app has been so extremely helpful. The structure of the app is so intuitive. It definitely helps with giving you an understanding of why something is wrong / right & making sure it sticks. Absolutely love it & I'm so grateful.

nikhildv

3 years ago

This app has been a great help, It gives perspective with the answers and that helps you prepare ... thanks for sharing it.

kerbs2CB

3 years ago

This app helped me pass my PMP today. The questions are not exactly as they are on the test but they help you with gaining the knowledge you need to pass the test! And it is free! I would recommend this to anyone studying for the PMP.

Leave a Reply

Your email address will not be published. Required fields are marked *

*