The project was going well until you recently discovered that the site of the offshore development team has just conducted an emergency evacuation due to a political rally that has become violent. This comes as a shock to the local project team. How could this have been prevented?

A By being aware of the project environment
Explaination

When managing a project, you should always be aware of the local laws affecting the project, as well as the political climate. By being aware of the political climate, the project team would have planned and taken preventive actions. The question is not necessarily asking you how to avoid the rally but, instead, how to prevent it from affecting the project.