Question:

The stakeholder approaches the project manager to report that the schedule must be adjusted to complete one week earlier than originally planned. If a predictive approach is practiced to manage the project, what would be the preferred approach for the project manager to take in order to make this occur?

A Fast-track the schedule
explanation

The project manager has told the scheduler that the schedule must be compressed by one week. That means that we will use one of two schedule compression techniques: crashing or fast-tracking, both of which are options. When possible, select the lowest-cost option first, which would be fast-tracking.