Question:

To expedite the scheduling process, a project manager alters an existing schedule management plan from a previous program for use on the current one. In this case, the schedule management plan reflects:

A An organizational process asset
explanation

Organizational process assets contain historical information from past archived projects, lessons learned, templates, policies, procedures, and other valuable information. In this case, the project manager is using a previous schedule management plan as a template and tailoring it for use by the current project. This is recommended practice and prevents having to reinvent the wheel for every project. Instead, the effort is placed on increasing the efficiency and refining existing practices and templates.

Related Information

Comments

edenegayle

4 years ago

I’m not sure how this app is accurate, simple & effective along with FREE? But I’m so grateful. Getting professional qualifications can be so expensive & daunting to tackle. This test taking, review-type app has been so extremely helpful. The structure of the app is so intuitive. It definitely helps with giving you an understanding of why something is wrong / right & making sure it sticks. Absolutely love it & I'm so grateful.

nikhildv

4 years ago

This app has been a great help, It gives perspective with the answers and that helps you prepare ... thanks for sharing it.

kerbs2CB

4 years ago

This app helped me pass my PMP today. The questions are not exactly as they are on the test but they help you with gaining the knowledge you need to pass the test! And it is free! I would recommend this to anyone studying for the PMP.

Leave a Reply

Your email address will not be published. Required fields are marked *

*