Question:

What actions can you take to aid speed up the project?

A Examine the project plan to see whether there are any phases that can be fast-tracked and then revise the project plan to reflect the compression of the schedule.
Explaination

Fast-tracking is the best answer in this scenario. Budget was the original constraint on this project, so it’s highly unlikely the project manager would get more resources to assist with the project. The next best thing is to compress phases to shorten the project duration.