Question:

What activity does Cheryl and the project manager practice?  

A Capturing lessons learned     
Explaination

Cheryl and the project manager are engaged in capturing lessons learned in engaging with this particular vendor and also in activities associated with managing the vendor’s performance; this includes discussing what went well and what could have been done differently, which will benefit future projects.