header bg

Scan QR code or get instant email to install app

Question:

What chart is the project manager and sponsor revising?

A Velocity chart
explanation

Velocity refers to the total story points that the team is completing on average per iteration. Velocity allows the team to forecast the rate at which they are burning down the work of the project. A velocity chart shows the sum of the estimates of work delivered across all iterations.