header bg

Question:

What is the most likely reason for the high degree of problems experienced in the project? (Select two.)

A A poorly written scope
Explaination

While all options may have contributed to the project issues, a poorly written scope can quickly result in project failure, no matter how good the change control procedures or systems are. A lack of formal project management may have contributed as well but being certified does not guarantee that this type of scenario will not occur. The scope baseline is often used for change. The scope baseline is often used for change control purposes and in making project decisions, which is why a poorly written scope will result in a large number of project changes for projects managed using a predictive life-cycle approach. Given that the project contained high ambiguity, issues may have been reduced by using an adaptive or hybrid life-cycle approach.