Question:

What should she do?

A Assess the impact of the new regulation on the project’s scope and update the backlog to reflect the necessary changes.
Explaination

Project managers must remain alert to change business landscape to understand the impact to their projects. When this occurs, such as in Kaylee’s case, project managers should assess and prioritize the impacts of these changes on their project and then adjust the backlog accordingly.