Question:
Which of the following best describes how Planning activities are presented in a highly adaptive (Agile) life cycle?
A
Progressive elaboration of scope is based on continuous feedback.
Explaination
In an Agile life cycle, Planning activities involve the progressive elaboration of scope, based on continuous feedback from stakeholders.