Question:

Which of the following comments should you keep in mind (and know to be true) regarding duration compression?  

A Schedule compression shortens the project schedule but doesn’t change the project scope. 
Explaination

Schedule compression shortens the project schedule without changing the project scope. Crashing doesn’t always give you a good alternative and typically increases project costs. Fast-tracking typically increases risk and necessitates rework.