Question:

Which of the following is a valid input that helps the project manager in operating the overall work of the project?

A Project documents
Explaination

The question refers to the Direct and Manage Project Work process, which is responsible for leading and performing the work defined in the project management plan and implementing any project management plan and implementing any changes that have been approved. This is where the project manager provides the overall management of the work being executed. Inputs to this process include the project management plan, project documents, approved change requests, enterprise environmental factors, and organizational process assets. Expert judgment is a tool and technique, while issue log and work performance data are outputs of the process.