Which of the following is not likely to be covered within the risk management plan?  

A When and how often to communicate with stakeholders throughout the project 
Explaination

While the risk management plan covers the details of risk-related reports and formats, it does not cover all of the communication requirements of project stakeholders. This is addressed within the communications management plan.