Question:

Which of the following project management Knowledge Areas include every team member and stakeholder on the project?

A Project Communications Management
explanation

Project Communications Management involves every member of the project team, including all the stakeholders. Everyone involved in the project Project Resources involve all the human and physical resources assigned to the work of the project. Although all the folks working on the project are involved, only the project manager and perhaps a few others are involved in performing the processes within this Knowledge Area.

Related Information

Comments

edenegayle

4 years ago

I’m not sure how this app is accurate, simple & effective along with FREE? But I’m so grateful. Getting professional qualifications can be so expensive & daunting to tackle. This test taking, review-type app has been so extremely helpful. The structure of the app is so intuitive. It definitely helps with giving you an understanding of why something is wrong / right & making sure it sticks. Absolutely love it & I'm so grateful.

nikhildv

4 years ago

This app has been a great help, It gives perspective with the answers and that helps you prepare ... thanks for sharing it.

kerbs2CB

4 years ago

This app helped me pass my PMP today. The questions are not exactly as they are on the test but they help you with gaining the knowledge you need to pass the test! And it is free! I would recommend this to anyone studying for the PMP.

Leave a Reply

Your email address will not be published. Required fields are marked *

*