header bg

Scan QR code or get instant email to install app

Question:

Which of the following statements are accurate? (Select three.)

A Plan Resource Management, Estimate Costs, and Control Procurements are all project management processes.
explanation

Estimate Activity Resources is a process that belongs to the Project Resource Management Knowledge Area. All other statements are true.