Question:

Which of the following statements are correct? (Select three.)

A The PDM displays activities on the node.
Explaination

Only the Arrow Diagramming Method (ADM) uses dummy activities, which are not real activities but instead are meant to show that a relationship between two activities exists. All other statements are accurate.