Question:

Which organizational process asset should you use when closing out a project or phase?

A Configuration management knowledge base
Explaination

Marketplace conditions and financial management and accounts payable systems are examples of enterprise environmental factors versus organizational process assets. When performing the Close Project or Phase process, project or phase closure guidelines or requirements, along with the configuration management knowledge base, serve as valuable inputs. The configuration management knowledge base contains versions and baselines of standards, base contains versions and baselines of standards, policies, procedures, and project documents belonging to the organization.