Question:

Which project should the committee select?

A Project A
Explaination

IRR is the discount rate when the present value of the cash inflows equals the original investment. Project C’s original investment equals the present value of its cash inflows at a discount rate of 7 percent. Therefore, Project A has the highest IRR and should be chosen above the other two.