Question:

While carrying out the Monitor and Control Project Work process, a project manager analyzes performance data to decide whether any corrective or preventive action is necessary. Which of the following is a valid input that can help the project manager in practicing this activity?

A Work performance information
explanation

Work performance information is a key input that the project manager needs to evaluate in and of itself). Work performance data, on the other hand, represents raw data that is used in executing the work; it later becomes information as it is analyzed against baselines through other processes that belong to the Monitoring and Controlling process group. The remaining two options are tools and techniques of the process, not inputs.

Related Information

Comments

edenegayle

4 years ago

I’m not sure how this app is accurate, simple & effective along with FREE? But I’m so grateful. Getting professional qualifications can be so expensive & daunting to tackle. This test taking, review-type app has been so extremely helpful. The structure of the app is so intuitive. It definitely helps with giving you an understanding of why something is wrong / right & making sure it sticks. Absolutely love it & I'm so grateful.

nikhildv

3 years ago

This app has been a great help, It gives perspective with the answers and that helps you prepare ... thanks for sharing it.

kerbs2CB

3 years ago

This app helped me pass my PMP today. The questions are not exactly as they are on the test but they help you with gaining the knowledge you need to pass the test! And it is free! I would recommend this to anyone studying for the PMP.

Leave a Reply

Your email address will not be published. Required fields are marked *

*