header bg

Question:

While carrying out the Monitor and Control Project Work process, a project manager analyzes performance data to decide whether any corrective or preventive action is necessary. Which of the following is a valid input that can help the project manager in practicing this activity?

A Work performance information
Explaination

Work performance information is a key input that the project manager needs to evaluate in and of itself). Work performance data, on the other hand, represents raw data that is used in executing the work; it later becomes information as it is analyzed against baselines through other processes that belong to the Monitoring and Controlling process group. The remaining two options are tools and techniques of the process, not inputs.