Question:

While performing activities connected to controlling project and product scope, a project manager discovers scope creep. Select the action which the project manager is likely to do next to take corrective action.

A Submit a change request and analyze the impact
Explaination

The project manager will need to analyze the impact of the scope change and what options exist, such as whether to undo what has been completed, or analyze whether the scope change should be approved. This should occur through the formal change control process via a change request.