Question:

Who is chartered with the authority to accept or deny change requests as defined by the organization?

A Change control board
Explaination

The change control board is officially chartered and given the authority to approve or deny change requests as defined by the organization and as outlined within the project management plan. The authority level (including exception or emergency process) should be detailed within the project management plan.