Question:

Who is correct?

A Both     
Explaination

Both processes are responsible for carrying out closure activities when it comes to procurements. The closed procurements output is a result of Control Procurements, where completed requirements are validated against the contract; administrative closure of procurements occurs through the Close Project or Phase process, including archiving related documentation.