Question:

Who is responsible for addressing conflict between the two project team members?

A The two project team members
Explaination

It’s often thought that the project manager or functional manager is responsible for resolving this type of conflict. But in actuality, these individuals should be brought in only to provide assistance or to address the conflict in a formal manner. The best option is that the project team members resolve the conflict on their own, directly.