Within a predictive life cycle, which of the following works as the basis for estimating costs?

A WBS
Explaination

The WBS serves as the basis for estimating costs. It is an input to the Estimate Costs process through the scope baseline, which is part of the project management plan. It contains all the project deliverables and the control accounts associated with work package elements.