Question:

Yasmin is a project manager tasked with putting together the project charter for a project that will generate a new line of gadgets for the company. After discussion with various key stakeholders, she starts drafting the document. Yasmin is considered to include all of the following factors within the project charter except for which one?

A List of detailed risks
explanation

Information included within the project charter is high level versus detailed. While the charter may include a list of high-level risks, it is unlikely that a detailed list can be compiled at this early stage of the project.