Question:

You are a project manager carrying out several activities that involve managing the team. At the moment, you are setting for your individual team members’ performance assessments. Which of the following will help you as you carry out this activity? (Select three.)  

A Work performance reports 
Explaination

You are carrying out activities associated with the Manage Team process. The following information will provide useful insight into team member performance: resource management plan, issue log, lessons learned register, project team assignments, team charter, team performance assessments, work performance reports, enterprise environmental factors, and organizational process assets. A project management information system is a tool versus information that would be used to assess performance.