You are a senior project manager operating in a manufacturing plant that produces components used by the aviation industry. You have just finalized team assignments. What step are you likely to perform next?  

A Develop the team by refreshing team skills 
Explaination

You have just completed activities associated with building the project team. Activities associated with developing the team are likely to follow.