Question:

You are a senior project manager working at a manufacturing plant that created components used by the aviation industry. You are taking a predictive life-cycle approach and are in the process of implementing approved changes. What main information will you need to successfully finish the associated activities?

A Approved change requests
explanation

The question refers to a key input of the Direct and Manage Project Work process, which is a process that provides overall management of the project work and deliverables. While several inputs are important, without the approved change requests, you cannot complete the activities referenced in the question.