You are currently appointed to work on a project involving the introduction of a new pharmaceutical drug. The vice president (VP) of strategic partnerships, who to date has not been a part of the project, asked to see the work performance data. This increases a red flag for the following reason:

A All stakeholders of the project have not been identified to date.
explanation

Based on the question, the VP is clearly a stakeholder of the project, which means that they were not previously identified. If all stakeholders expectations, needs, and requirements have not been fully documented and resolved, which can create major issues within the project.