Question:

You are exercising the tools and techniques of the Control Schedule process and know all of the following are correct except which one?

A Delays to noncritical path activities will not cause schedule delays.
Explaination

Only critical path activities will cause schedule delays unless one or more of the noncritical-path activities have used up all their float time. This question doesn’t specify that a noncritical-path activity has used all its float time.