Question:

You are in the Planning stage of the project and have just started to produce the cost baseline. In what activity are you engaged as a project manager?

A Performing the Determine Budget process
Explaination

You are performing the Determine Budget aggregate the estimated costs of individual activities or work packages to establish an authorized cost baseline.