You are managing a project on contract. Your bonus is contingent on the timely completion of the project. The project is behind schedule, but the remaining tasks are easy to finish and won’t take more than a week. Which of the following is the most appropriate react?

A Tell the customer about the delay and negotiate a change to the schedule and/or invoice payment date and then bill for the full amount when the work is completed.
Explaination

The most appropriate response is to tell the customer about the remaining tasks and work with them to modify the schedule date or modify the agreement regarding the payment date.