Question:

You are operating on the risk management plan for your current project and need to record how the risk activities will be recorded for the advancements of future projects. Which part of the risk management plan addresses these issues?

A Tracking
Explaination

Tracking includes a description of how you’ll document the history of the risk activities for the current project and how the risk processes will be audited. This section of the risk management plan is also helpful for lessons learned.