Question:

You use a predictive approach to managing projects and have just finished your cost baseline. Next, you start working on determining funding requirements. Which of the following is correct?

A Management reserves are the difference between the funding requirements and the cost baseline.
explanation

The funding requirements are derived from the cost baseline. Management reserve is released in increments throughout the project, and the funding requirements are an output of the Determine Budget process.

Related Information

Comments

edenegayle

4 years ago

I’m not sure how this app is accurate, simple & effective along with FREE? But I’m so grateful. Getting professional qualifications can be so expensive & daunting to tackle. This test taking, review-type app has been so extremely helpful. The structure of the app is so intuitive. It definitely helps with giving you an understanding of why something is wrong / right & making sure it sticks. Absolutely love it & I'm so grateful.

nikhildv

4 years ago

This app has been a great help, It gives perspective with the answers and that helps you prepare ... thanks for sharing it.

kerbs2CB

4 years ago

This app helped me pass my PMP today. The questions are not exactly as they are on the test but they help you with gaining the knowledge you need to pass the test! And it is free! I would recommend this to anyone studying for the PMP.

Leave a Reply

Your email address will not be published. Required fields are marked *

*