You use a predictive approach to managing projects and have just finished your cost baseline. Next, you start working on determining funding requirements. Which of the following is correct?

A Management reserves are the difference between the funding requirements and the cost baseline.
Explaination

The funding requirements are derived from the cost baseline. Management reserve is released in increments throughout the project, and the funding requirements are an output of the Determine Budget process.