Question:

You work as a project manager and are meeting with your team. The target of this meeting is to determine which processes you should use to effectively operate the project. Which of the following describes what you’re practicing?

A Tailoring
explanation

Tailoring involves determining which project management processes to use when managing and conducting the project.