Question:

You work as the project manager for a project that will manufacture a mobile phone application that sends alerts when UV rays are at fatal levels, alerting users to stay indoors. You are in the process of measuring schedule performance against the schedule baseline. Within a predictive life cycle, what process group are these activities related to?

A Monitoring and Controlling
Explaination

You are currently performing activities associated with the Control Schedule process, which is part of the Monitoring and Controlling process group.