Question:

You work as the project manager for Ooh La Beauty Products. Your project is  developing a new line of bath products. You also serve on the change control board, which has just accepted a scope change. You know that which of the following statements are correct? (Select three.)  

A Scope changes include modifications to the agreed-upon WBS. 
Explaination

Scope changes might affect the schedule, cost, quality, and other processes and should be thoroughly integrated with all the Monitoring and Controlling processes. Scope changes may reduce the project requirements and thus reduce the number or hours needed to complete the project. This, in turn, could cause a reduction in the project budget.