header bg

Scan QR code or get instant email to install app

Question:

You work for Sergio’s, a golf equipment producer. Your organization is installing some new manufacturing equipment, and you are operating the project. Some risk events have come to fruition on the project, and as a result, change requests have been approved. You are in the Monitor Risks process and know that all of the following are correct regarding this question except for which one?

A Change requests will not take the form of preventive actions because you are in the Monitoring and Controlling process group and too far into the work of the project.
explanation

Change requests may take the form of preventive or corrective actions or workarounds. It’s not too late to take preventive action in the Monitoring and Controlling process group.

Related Information

Comments

edenegayle

4 years ago

I’m not sure how this app is accurate, simple & effective along with FREE? But I’m so grateful. Getting professional qualifications can be so expensive & daunting to tackle. This test taking, review-type app has been so extremely helpful. The structure of the app is so intuitive. It definitely helps with giving you an understanding of why something is wrong / right & making sure it sticks. Absolutely love it & I'm so grateful.

nikhildv

3 years ago

This app has been a great help, It gives perspective with the answers and that helps you prepare ... thanks for sharing it.

kerbs2CB

3 years ago

This app helped me pass my PMP today. The questions are not exactly as they are on the test but they help you with gaining the knowledge you need to pass the test! And it is free! I would recommend this to anyone studying for the PMP.

Leave a Reply

Your email address will not be published. Required fields are marked *

*