Question:

You work for Sergio’s, a golf equipment producer. Your organization is installing some new manufacturing equipment, and you are operating the project. Some risk events have come to fruition on the project, and as a result, change requests have been approved. You are in the Monitor Risks process and know that all of the following are correct regarding this question except for which one?

A Change requests will not take the form of preventive actions because you are in the Monitoring and Controlling process group and too far into the work of the project.
explanation

Change requests may take the form of preventive or corrective actions or workarounds. It’s not too late to take preventive action in the Monitoring and Controlling process group.