Your project includes a new manufacturing technique that requires knowledge of chemical engineering to perform one of the services required in the project management plan. The service was performed, and as a result, an approved change request has been submitted. Which of the following statements is correct?  

A Approved change requests are inputs to the Direct and Manage Project Work process, and the Direct and Manage Project Work process will be repeated in order to implement this change. 
explanation

Approved change requests are an input to the Direct and Manage Project Work process. This process will be repeated to implement the change. Approved change requests come about as a result of the approved change requests output of the Perform Integrated Change Control process. There is not enough information in the question to determine whether the scope has increased, so the other answers are incorrect.

Related Information

Comments

edenegayle

4 years ago

I’m not sure how this app is accurate, simple & effective along with FREE? But I’m so grateful. Getting professional qualifications can be so expensive & daunting to tackle. This test taking, review-type app has been so extremely helpful. The structure of the app is so intuitive. It definitely helps with giving you an understanding of why something is wrong / right & making sure it sticks. Absolutely love it & I'm so grateful.

nikhildv

3 years ago

This app has been a great help, It gives perspective with the answers and that helps you prepare ... thanks for sharing it.

kerbs2CB

3 years ago

This app helped me pass my PMP today. The questions are not exactly as they are on the test but they help you with gaining the knowledge you need to pass the test! And it is free! I would recommend this to anyone studying for the PMP.

Leave a Reply

Your email address will not be published. Required fields are marked *

*