Question:

Your project selection committee is estimating three projects. They are using a weighted scoring model that has three criteria: decrease training time, streamline customer support functions and return on investment. The weights for these criteria are 5, 4, and 2, respectively. Your selection committee has completed scoring the three projects and has given you the scores for the three criteria. They are as in the figure. Which project should you select based on the scores from the weighted scoring model?

A Project 1
Explaination

According to the Agile Practice Guide, the definition of done (DoD) refers to a team’s checklist of all the criteria required to be met so that a deliverable can be considered ready for customer use. Acceptance criteria refer to a set of conditions that must be met before deliverables are accepted.