Question:

Your project sponsor has asked you for a prediction of the likely cost to finish the work of the project. Which of the following statements is correct?

A You’ll use the ETC calculation, which is part of the forecasting tool and technique of the Control Costs process.
Explaination

This is the estimate to complete (ETC) calculation, which will estimate the remaining work of the project. The ETC calculation is part of the forecasting tool and technique of the Control Costs process.